Worked scenario
Made to the drawing, wrong for the room
Interiors are made to a snapshot of a site that continues changing after the snapshot was taken.
3 min read
A survey produces dimensions. Manufacture follows weeks later. In between, other trades have worked in the same space.
The snapshot ages
Plaster, flooring and services all reduce a room. A unit built to pre-plaster dimensions does not fit, and the fault is genuinely nobody's — but the cost lands on whoever manufactured.
Re-check is cheaper than rework
A confirmatory measurement before cutting costs an hour. Rework costs material, manufacturing time and an installation slot, and it usually arrives with a delayed handover.
Attribute the cause
Rework recorded without a cause becomes a general quality concern. Split into survey error, site change and manufacturing error, it usually turns out to be dominated by one, and only one of the three is addressed by being more careful in the workshop.
What changes
- Survey date recorded with the measurements
- Re-check before manufacture where site work is ongoing
- Site changes notified by the contractor as an agreed obligation
- Rework attributed to survey, site change or manufacture